The following is the general assembly method for hard alloy cold heading molds:
Step 1: Preparation work
Clean the installation area and various components of the mold to ensure that there are no impurities, oil stains, etc.
Step 2: Install the concave mold
Place the concave mold steadily in the corresponding installation position and perform preliminary positioning through positioning pins or other positioning devices.
Step 3: Install the convex mold
Carefully align the convex mold with the concave mold, adjust the gap according to the design requirements, and then fix the convex mold.
Step 4: Tighten the connection
Use appropriate bolts, nuts, and other fasteners to firmly connect the various components of the mold together, but pay attention to the appropriate tightening force to avoid being too tight or too loose.
Step 5: Check and Adjust
Check the overall assembly condition of the mold, including gaps, coaxiality, etc., and make minor adjustments if necessary to ensure that the mold is in good working condition.
Step 6: Trial molding
Before formal production, conduct a trial mold operation to observe whether the mold runs smoothly and whether the molding effect meets the requirements. If there are any problems, make adjustments in a timely manner.
It should be noted that the specific assembly methods may vary depending on the mold structure and production requirements, and the assembly process should be strictly operated in accordance with relevant process and technical requirements.